Answer:
The total cost of making the tank equals $2,082.48
Explanation:
Giving the following information:
The tank requires 208 sq ft of material at $9.29 per square foot.
It also requires 4.5 hours of labor at $26.40 per hour plus 1.6 hours of labor at $19.60 per hour.
To calculate the total cost, we need to multiply the unitary variable cost by the total amounts:
Direct material= 9.29*208= $1,932.32
Direct labor= 4.5*26.4 + 1.6*19.6= $150.16
The total cost of making the tank equals $2,082.48