Answer:
The bakery should hire fewer doughnut bakers and more bagel makers to maximize profits.
Step-by-step explanation:
From the question, we have:
MRP of the last doughnut baker hired = $35
MRP of the last bagel baker hired = $15
Cost of doughnut bakers per day = $40
Cost of bagel bakers per day = $10
Decision criteria are that:
1. When the MRP is greater than Cost per day, hire more.
2. When the MRP is less greater Cost per day, hire fewer.
Since from the above, we have:
1. MRP of the last doughnut baker hired < Cost of doughnut bakers per day => $35 < $40
2. MRP of the last bagel baker hired > Cost of bagel bakers per day => $15 > $10
Therefore, the bakery should hire fewer doughnut bakers and more bagel makers to maximize profits.