Answer:
c. >60
Step-by-step explanation:
Given that:
Overage (CO) = 125
Shortage (CS) = 300
The Service level =
![(CS)/(CS+CO)](https://img.qammunity.org/2021/formulas/business/college/t8el6q0838esi7332i18q1omrwseoh0gjs.png)
![=(300)/(300+125)](https://img.qammunity.org/2021/formulas/business/college/g4y3l2shjd9l5x8w83q6ru7uo34agplwhq.png)
![=(300)/(425)](https://img.qammunity.org/2021/formulas/business/college/mxs2wrmhpx33idfbmxg6jabdpzw9sxaoqt.png)
= 0.7059
The Z value of 0.7059 is 0.55
where;
the mean
= 60
the standard deviation
= 20
Optimal booking =
![\mu +(Z * \sigma)](https://img.qammunity.org/2021/formulas/business/college/m6o3ad00mxm3w8xdd11ucgd8x97j56ogut.png)
Optimal booking = 60 + (0.55 × 20)
Optimal booking = 60 + 11
Optimal booking = 71