Answer:
Step-by-step explanation:
The Earned Value Analysis for each term can be computed as follows:
Term Acronym Formula Value
Budget At Completion BAC =1000×500 500,000
Planned Value PV =400×500 200,000
Earned Value EV =500000×0.45 225,000
Actual Cost AC 250,000
Cost Variance CV
-25,000
Schedule Variance SV
25,000
Cost Performance Index CPI
0.9
Schedule Performance Index SPI
1.125
Estimate At Completion EAC
555,556
Estimate To Complete ETC
305,556
Variance At Completion VAC
-55,556