Answer: a. $680,000
Step-by-step explanation:
Gross profit to be recognized from entire project;
= Value of building - cost
= 22,800,000 - 20,800,000
= $2,000,000
In 2021, a cost of $7,072,000 was incurred out of the total cost of $20,800,000.
Percentage complete is therefore;
= 7,072,000/20,800,000
= 34%
The gross profit recognized is therefore;
= 34% * Total gross profit
= 34% * 2,000,000
= $680,000