30 men repair a road in 56 days by working 6 hours daily. In how many days 45 men will repair the same road by working 7 hours daily?

User MattSkala
by
8.4k points

1 Answer

4 votes

Explanation:

(30 men, 56 days, 6 hours daily)

=> (30 men, 48 days, 7 hours daily)

=> (45 men, 32 days, 7 hours daily)

Hence it will take 32 days.