187k views
5 votes
g Corporation's cost formula for its bungalow operating cost is $2,960 per month plus $326 per day. For the month of December, the company planned for activity of 20 days, but the actual level of activity was 18 days. (ID#17794) The actual bungalow operating cost for the month was $9,770. Q) What would be the spending variance for Blonok985's bungalow operating cost in December (closest to)?

1 Answer

3 votes

Answer: $942 U

Step-by-step explanation:

Budgeted cost was $2,960 per month plus $326 per day and there were 18 days of actual activity.

Budgeted cost = 2,960 + 326 * 18

= $‭8,828‬

Variance = Budgeted cost - Actual cost

= ‭8,828‬ - 9,770

= -$942

Budgeted cost is less than Actual cost which means the Variance is UNFAVORABLE.

User Dilan Premarathna
by
7.8k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.