Answer: $1000
Step-by-step explanation:
To calculate the normal cost of this activity, we will use the formula:
Cash slope = (Crash cost - Normal cost) / (Normal duration - Crash duration)
250 = (1500 - Normal cost) / (15 - 5)
250 = (1500 - Normal cost) / 10
Cross multiply
(250 × 10) = 1500 - Normal cost
2500 = 1500 - Normal cost
Normal cost = 2500 - 1500
Normal cost = $1000