Answer:
service level is 90.78% ( it falls on cumulative probability of 1.00 or 100%)
Therefore the quantity of spares that should be ordered is 3
Explanation:
Given that;
spares cost = $179 each
salvage value = $49 each
distribution of the probability of usage;
Number Probability cumulative Probability
0 0.05 0.05
1 0.60 0.65
2 0.20 0.85
3 0.15 1.00
Now
the cost of stock-out (underestimation) Cu
= $640 per day × 2 days = $1,280
the cost of excess inventory (overestimation) Co
= Unit cost - salvage value = $179 - $49 = $130
Therefore Service Level = Cu / ( Cu + Co )
we substitute
Service Level = $1,280 / ( $1,280 + $130 )
= $1,280 / $1410
= 0.9078 or 90.78%
so service level is 90.78% ( it falls on cumulative probability of 1.00 0r 100%)
Therefore the quantity of spares that should be ordered is 3