Answer:
$97,700
Step-by-step explanation:
Firms which are involved in the manufacturing of products must determine the cost of goods manufactured. Thus, this is where this calculation is applicable.
To determine the Cost of Goods Manufactured, a Manufacturing schedule must be prepared. This Schedule includes all the costs of manufacturing a product (direct and indirect) as well as details about work in process inventory as below :
Manufacturing schedule
Direct materials cost $19,100
Direct labor cost $24,600
Factory overhead $54,600
Add Beginning work in process inventory $10,800
Less Ending work in process inventory ($11,400)
Cost of goods manufactured $97,700