Answer:
D) 18%.
Step-by-step explanation:
The WACC for this new project = Current WACC + Adjustment Factor (High Risk)
WACC for this new project = 12% + 6%
WACC for this new project = 18%
Note: Attached as picture shows the reason for the chosen Adjustment factor