Answer: $4.18
Step-by-step explanation:
Material price variance = (Standard price - Actual price) * Actual quantity
-9,000 = (4 - P) * 50,000
-9,000 = 200,000 - 50,000P
50,000P = 200,000 + 9,000
P = 209,000/50,000
P = $4.18
5.8m questions
7.5m answers