In class, we discussed the I C B (Information Controls Buffers) Portfolio. Under this concept, we would not need any buffers if we have:

a. no information and no control
b. perfect information and perfect control
c. some information and some control
d. perfect information and some control
e. some information and perfect control

User MortenB
by
4.6k points

1 Answer

4 votes

Answer:

b) perfect information and perfect control

Step-by-step explanation:

The IC buffer portfolio is needed, considering possibility of information forecast error & inventory control non instantaneous nature.

In case there is perfect information - regarding timing & accuracy, and perfect control - referring instantenity regarding actions. Then, I C B (Information Controls Buffers) Portfolio is not needed.