During self-construction of an asset by Richardson Company, the following were among the costs incurred: Fixed overhead for the year $1,000,000 Portion of $1,000,000 fixed overhead that would be allocated to asset if it were normal production 80,000 Variable overhead attributable to self-construction 100,000 What amount of overhead should be included in the cost of the self-constructed asset

1 Answer

5 votes

Answer:

$180,000

Step-by-step explanation:

Amount of overhead should be included in the cost of the self-constructed asset = Fixed overhead that would be allocated to asset + Variable overhead attributable to self-construction

= $80,000 + $100,000

= $180,000

Thus, $180,000 is the amount of overhead that should be included in the cost of the self-constructed asset.