Answer:
6.85%
Step-by-step explanation:
Mean = 575,234
Standard deviation = 10,245
Project will be successful when PV > 560,000
For not getting success, PV < 560,000
P (X < 560,000) = P (Z < (560,000-575,234)/10,245)
P (X < 560,000) = P (Z < -1.48697)
P (X < 560,000) = 0.0685
P (X < 560,000) = 6.85%
Therefore, the chance that the project will NOT succeed is 6.85%