Answer:
d. Decrease by 0.045 minutes
Step-by-step explanation:
First Case
Time per unit for 250 batch size = (30 / 250) + 5 minutes
Time per unit for 250 batch size = 5.12 minutes
Second case
Time per unit for 250 batch size = (30 / 400) + 5 minutes
Time per unit for 250 batch size = 5.075 minutes
The decrease in manufacturing time = Old-time - New time = 5.12 - 5.075 = 0.045 minutes . So, it Decrease by 0.045 minutes