Mark, a project manager for a bottling company, has a $500,000 budget. As of today's date, $100,000 has been spent on the project. What is the project's actual cost?

a. $500,000
b. $400,000
c. $250,000
d. $100,000

User Mdirolf
by
4.7k points

1 Answer

6 votes
B. 400,000

Because you do 500,000 minus 100,000 to get the answer and which the answers is 400,000
So the project actual cost 400,000