3.2k views
5 votes
Question 9 of 10

Stiviko's approved work plan included 4 technicians to create 200 web pages
over 5 days. What was the unit metric for the production work?
O A. 10 pages per technician per day
B, 40 pages per technician per day
C. 20 pages per technician per day
D. 400 web pages per week
SUBMIT
PREVIOUS

1 Answer

1 vote

Answer:

A.

Step-by-step explanation:

they make 40 a day because 200 / 5 = 40

User Chanckjh
by
8.4k points