The Coca-Cola Company uses a job-order costing system. True or False: Job-order costing uses the actual direct materials cost of the job, the actual direct labor cost of the job, and the manufacturing overhead cost applied to the job.

User Yunbin Liu
by
3.4k points

1 Answer

11 votes

Answer: In managerial accounting, there are two general types of costing systems to assign costs to products or services that the company provides: “job order costing” and “process costing”. Job order costing is used in situations where the company delivers a unique or custom job for its customers. Every customer is treated uniquely and delivered products to specifically suit their individual needs.