Answer:
Flexible budget cost materials and supplies= $2,720
Step-by-step explanation:
In the flexible budget, we need to multiply the standard quantities by the actual activity.
Standard cost formula:
materials and supplies= 1,950 + 14*x
x= number of vehicles
For 55 vehicles:
Flexible budget cost= 1,950 + 14*55
Flexible budget cost= $2,720