You are a new project manager who has been entrusted with a project. The project has entered the Execution phase, and you as the project manager, discover that there is a need to spend part of the project funding to bring an external consultant, to cover for an employee leaving the project team. If you are authorized to make decisions about spending this project fund, what kind of an organization structure are you working in?

User Ran Hassid
by
4.8k points

1 Answer

1 vote

Answer:

Project ( Projectized)

Step-by-step explanation:

project management simply entails thorough planning, organizing, and managing resources to bring about the successful completion of specific project goals and objective.

3 main types of organizational structures are functional (departmentalized), matrix, and project.

In projectized - an organizational structure, the project manager has full power to assign works, apply resources, and direct the work of persons that is assigned to the project.

It is characteristized by subject matter experts (SMEs) from different functional areas are assigned to directly report to the project manager (PM) for a specific project and others.