When budgets are used for evaluation, what is the difference between budgeted and actual amounts called?

a. Exceptions
b. Budget variances
c. Performance results
d. Flexible budgets

User Ashraf
by
4.2k points

1 Answer

4 votes

Answer:

b. Budget variances

Step-by-step explanation:

The difference between budgeted and actual amount is called as budget variance. Budget variance is useful when we are evaluating the performance of a company, this is done be deducting the budgeted amount from actual amount to see if the performance of a company is favorable or unfavorable