Answer:
$1,495,000
Step-by-step explanation:
From the above, we can infer that the first two costs for equipment and software are fixed cost, while wages is the cost that is influenced by the number of months (m).
The above implies that we would multiply number of months 'm' with $40,000.
= 840,000 + 15,000 + 40,000m
Where month (m) = 16
= 840,000 + 15,000 + 40,000(16)
= 840,000 + 15,000 + 640,000
= $1,495,000
Therefore, the total cost is $1,495,000