Answer: $2,200 Unfavorable
Step-by-step explanation:
Volume variance is the difference between actual and budgeted output so can be calculated by;
= (Budgeted output - Actual output) * overhead rate
= (4,900 - 3,800) * 2
= $2,200 Unfavorable
Unfavorable because they produced less than the budget indicated that they would.