Answer:
37 units
Step-by-step explanation:
lead time = 5 weeks
service level = 90%, z score = 1.645
average demand = 40 units per week
standard deviation = 10 units per week
safety stock = z-score · √lead time · standard deviation of demand = 1.645 · √5 weeks · 10 units per week = 1.645 · 2.236 · 10 = 36.78 ≈ 37 units
the reorder point = (5 weeks x 40 units per week) + safety stock = 200 + 37 = 237 units