Answer:
88 hours
Explanation:
Since we are decreasing the number of machines by a factor of four and all the machines work at the same rate, we are simply going to increase the work hours by a factor of 4
Increasing the work hours by a factor of 4 will yield 22 * 4 = 88 hours
So it will take 88 hours to fill the order if the number of machines is deceased by a factor of 4