What is the hourly utilization rate of each resource if the bottleneck(s) work nonstop during a 10-hour day?

User Mosely
by
4.8k points

1 Answer

6 votes

Answer:

100%

Explanation:

Utilization rate =

Hours worked / total working hours per day

Since the bottle works nonstop during a 10-hour day, it worked 10 hours

Utilization rate in percentage = (10/10)×100%

= 100%