Gantt charts are effective for project scheduling if:

a. Activities are highly interconnected
b. Activity times are random
c. The project contains simple activity sequences
d. All of the above

User Ronquiq
by
7.5k points

1 Answer

1 vote

Answer: c. The project contains simple activity sequences

Step-by-step explanation:

Gantt chart is a firm of bar chart that depicts a project schedule as it helps in the scheduling of a particular project.

Gantt chart is a graphical tool that helps in showing the activities that are performed against time to the project team or project manager. Gantt charts are effective for project scheduling if such project contains simple activity sequences.