Answer:
24,000 units
Step-by-step explanation:
Demand per period, = 8,000 units
Lead time, LT (in periods) = 3 weeks
Average demand during lead time = Lead Time * Demand per period
Average demand during lead time = 8,000 units * 3 weeks
Average demand during lead time = 24,000 units
Thus, our average requirements during the lead time of 3 weeks is 24,000 units