Answer:
The way recording this amount is shown in explanation
Step-by-step explanation:
Billings on construction in the process will be deducted from the amount of construction in the process. Further records will be shown in the balance sheet as below
BALANCE SHEET
Current Assets
Account Receivables $262,000
Inventories
Construction in process $1,846,000
less: billings (900,000)
Cost in excess of billing $946,000