Answer:
C. Step cost
Step-by-step explanation:
A step cost is the cost that do not varies with the change in the volume of an activity. It is to be considered as a fixed cost having some kind of specific boundaries. If it is beyond that it would be changed
Therefore in the given situation, for the number of machines, the maintenance cost should be term as a step cost and the same is to be considered