the department of transportation (DOT)sends a crew of workers to fix a pothole in front of North Mecklenburg High School. It takes 12 workers a total of 8 hours to finish the job. How long will the job
asked
Oct 19, 2021
201k
views
4
votes
the department of transportation (DOT)sends a crew of workers to fix a pothole in front of North Mecklenburg High School. It takes 12 workers a total of 8 hours to finish the job. How long will the job take if 2 workers call in sick?
Mathematics
high-school
Ray Wadkins
asked
by
Ray Wadkins
8.5k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
3
votes
Answer: 9.6
Explanation:
Spickermann
answered
Oct 25, 2021
by
Spickermann
6.9k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.3m
questions
12.1m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org