You have been asked by the CEO of your company to manage a really important project. The CEO suggested five employees to be on your project team. You now think about the right organizational structure. Under what project management structure would these five employees face the least trade-offs with their current responsibilities

User Kdaveid
by
7.3k points

1 Answer

4 votes

Answer:

Dedicated project team

Step-by-step explanation:

Team members would face the least trade-offs with their current responsibilities in the dedicated project team.

Here we have a team that is grouped to work together in a single project organizational structure. The project manager is responsible for the team. He has the main authority. Members of the team work under humans he reports to the sponsor of the project. This structure is the easiest to create good team culture