Answer:
OEE=35.20%
Step-by-step explanation:
Calculation for the OEE of the equipment
Using this formula
OEE = Value add time / Total time available
Let plug in the formula
OEE= (169 x 3) / (24 hours a dayx 60 minutes)
OEE= 507 / 1,440
OEE= 0.3520*100
OEE=35.20%