1.Processes A, B, C, D, E, and F require service times of 3, 5, 2, 5, 3, and 5. Their arrival times are 0, 1, 3, 9, 10, and 12. What is the average turnaround time, waiting time, response time, and throughput when using SRJF, RR (q

User Rarst
by
5.1k points

1 Answer

5 votes

Answer:

please check attachment for the answers I gave. they are in tabular form

Step-by-step explanation:

1.Processes A, B, C, D, E, and F require service times of 3, 5, 2, 5, 3, and 5. Their-example-1
1.Processes A, B, C, D, E, and F require service times of 3, 5, 2, 5, 3, and 5. Their-example-2