Answer:
$186,600
Step-by-step explanation:
The computation of the predetermined overhead rate is shown below:
= Estimated manufacturing overhead / expected tptal labor hours
= $264,000 / 22,000 hours
= $12
Now for determining the total amount of bill first determine the total cost which is shown below:
Total cost is
= Direct material + direct cost + overhead cost
= $32,000 + 1,200 * $65 + 1,200 * $12
= $32,000 + $78,000 + $14,400
= $124,400
Now the total amount of the bill is
= 150% of $124,400
= $186,600