Answer:
required investment:
building costs = $48 million
decommissioning costs = $3 (at the end of year 3)
benefits:
year 1 = $15,900,000
year 2 = $18,900,000
year 3 = $19,000,000
discount rate = 4%
I rounded my calculations to the nearest thousand:
a) NPV = -48 + 15,900/1.04 + 18,900/1.04² + 16,000/1.04³ = -$1,013,000
b) NPV = -48 + 15,900 + 18,900/1.04 + 19,000/1.04² - 3/1.04³ = $973,000
c) NPV = -48 + 15,900/1.04⁰°⁵ + 18,900/1.04¹°⁵ + 19,000/1.04²°⁵ - 3,000/1.04³ = -$31,000
d) From a strictly financial point of view and only considering the 3 previous calculations, the project should be rejected. Two out of 3 options yield a negative NPV.