Answer: Option D $97,282 is correct
Explanation:
Materials Conversion
Units completed and transferred 12200 12200
Ending work in process 4900 2940 =4900*60%
Equivalent units 17100 15140
Materials Conversion Total
Equivalent units 17100 15140
X Cost per Equivalent unit 5.00 4.00
Total costs 85500 60560 146060
Total costs 146060
Less: Cost of beginning work in process 48778 =24012+24766
Cost of units started into production 97282