An engineering team has a goal of developing a bicycle frame that is both

lighter and stronger than previous models. Which cost-benefit analysis has
left out potential risks?

A.increased sales compared to employee stress and loss of natural resources

B. Better function compared to ecological damage of mining materials and research a development time

C. Better function compared to uncertain supply of materials and research a development time

D. Increased sales compared to research and development time and cost of materials

User RandyMy
by
4.5k points

2 Answers

1 vote

Answer:D. Increased sales compared to research and development time and cost of materials

Step-by-step explanation:

User Jclehner
by
4.8k points
7 votes

Answer:

D

Step-by-step explanation:

D