Answer:

Retrospective

Step-by-step explanation:

These are options for the question;

a.stakeholder analysis

b.lessons learned

c.plus-delta process

d.Retrospective

We were told from the question that an item to be recorded on the project meeting minutes is an evaluation of both good and poor points from the meeting. Then since the evaluation involves both good and poor points On agile projects, the evaluation is called the retrospective.

It should be noted that retrospective provide a way of measuring the degree in which the goals of the organization are been met. And make sure that degree of success is high as possible.