What is the MIRR of a project with the following cash flows? The WACC = 11.9%. Year 0 1 2 3 Cash Flow -100 50 50 50 Group of answer choices 19.0% 11.9% 23.4% Cannot be determined without knowing the IRR. CHEGG

User Sidhom
by
7.8k points

1 Answer

4 votes

Answer:

the MIRR of a project is 19.0%.

Step-by-step explanation:

The First Step is to Calculate the Terminal Value at end of year 3.

Terminal Value (FV) = Sum of (PV x (1 + r) ^ 3 - n)

= $50 x (1.119) ^ 2 + $50 x (1.119) ^ 1 + $50 x (1.119) ^ 0

= $62.61 + $55.95 + $50.00

= $168.56

The Next Step is to Calculate the MIRR using a Financial Calculator :

-$100 CFj

0 CFj

0 CFj

$168.56 CFj

Shift IRR/Yr 19.0104% or 19.0%

Therefore, the MIRR is 19.0%.