Answer:
b) false
Step-by-step explanation:
The basic classifications of project priorities are cost, time and performance. Profit is not included in the list, cost is included.
A project manager must decide how to manage the trade offs between cost, time and performance. E.g. if you want something well done and cheap, you cannot expect to have it done fast. If you want something done well and fast, it wouldn't be cheap.