The Project Evaluation and Review Technique (PERT) was developed as a means of scheduling and controlling projects with constant activity times. Group of answer choices False True

1 Answer

0 votes

Answer: False

Step-by-step explanation:

The Program Evaluation and Review Technique (PERT) is used to know the schedule tasks and also know the critical path variation. It is useful to know the length of time that'll be needed for the completion of every task and how it relates to others in order to know the entire time needed to complete the particular project.

The Project Evaluation and Review Technique (PERT) is not a means of scheduling and controlling projects with constant activity times. The activity time normally varies.