Answer:
The net present value of the proposed mining project is - $163,621.41.
Step-by-step explanation:
The Summary of Cash flows is as follows :
Year 0 : - ($ 380,000 + $ 120,000) = - $500,000
Year 1 : $ 135,000
Year 2: $ 135,000
Year 3: $ 135,000 - $ 44,000 = $91,000
Year 4: $ 135,000 + $ 69,000 + $ 120,000 = $324,000
Determine the Net Present Value of the mining project as follows :
Using a Financial Calculator, entries will be as follows
- $500,000 CFj
$ 135,000 CFj
$ 135,000 CFj
$91,000 CFj
$ 135,000 CFj
18 % I/YR
SHIFT NPV - $163,621.41