Mr. Green contracts with Mr. Brown to repair his roof. Mr. Brown is about 75% done when the deadline of the contract occurs. Which legal standard would prevent Mr. Brown from being considered to be in breach of his agreement with Mr. Green?

User Aelkz
by
4.9k points

1 Answer

1 vote

Answer:

Substantial performance standard

Step-by-step explanation:

Substantial performance standard refers to the legal standard in which the good and faith attempt is made so that the requirements of the contract or agreement could be performed

even if is not meet the requirements so we assume that the performance should be completed if its main motive is fulfilled

Therefore in the given case, the substantial performance standard is the correct option that fits to the situation