Answer:
Step-by-step explanation:
a )
Discount rate is 0%
NPV of first project = 85
NPV of second project = 0 + 0 + 104 = 104
second project is preferrable .
b )
if discount rate is 10%
NPV of first project = 85
NPV of second project = 104 / 1.1²
= 85.95
Their NPV is almost the same so anyone can be preferred .
c ) IRR can not be calculated unless the cost of project or cash outflow is given .