Answer:
The answer is:
A - Non-value-added
B - Non-value-added
C- Value-added
D- Non-value-added
E - Value-added
F - Value-added
G - Non-value-added
H- Non-value-added
Step-by-step explanation:
In activity-based costing, Non-value-added activities are activities that add costs to ones product without enhancing the value while value-added is a cost that enhance the quality of a product or service.
A - Non-value-added
B - Non-value-added
C- Value-added
D- Non-value-added
E - Value-added
F - Value-added
G - Non-value-added
H- Non-value-added