The critical path in a project network is:______ A. The Shortest path through the network. B. Longest path through the network. C. Network path with the most difficult activities. D. Network path using the most resources.

User Necevil
by
4.5k points

1 Answer

2 votes

Answer:

B

Step-by-step explanation: