Answer:
The company has developed standard costs for one unit of fludex, as follows: During November, the following activity was recorded relative to production of fludex.
Step-by-step explanation:
1) Real Price in Material Price Variance = 225000/12000 = 18.75
2) Standard Quantity in Material Quantity Variance = 3750*2.5 = 9375
3) Real Quantity in Material Quantity Variance = 12000 - 2500 = 9500
4) Real Hours in Labor Rate Variance/Labor efficiency Variance = 35*160 = 5600
5) Common Hours in Labor efficiency Variance/Variable Overhead efficiency Variance = 1.4*3750 = 5250
6) Real Rate in Variable Overhead Rate Variance = 18200/5600 = 3.25