188k views
0 votes
It took $4$ days for $75$ workers, all working together at the same rate, to build an embankment. If only $50$ workers had been available, how many total days would it have taken to build the embankment?

1 Answer

3 votes

Answer:

2.67 days

Explanation:

75/4=18.75

18.75/50=2.67

User Matthias Wimmer
by
6.1k points